TCN terminates 4 delayed power contracts, completes projects

The Transmission Company of Nigeria (TCN) has terminated about four power transmission contracts which it said were delayed because the contractors lack the capacity, and has engaged its engineers to complete them. 

 

SPONSOR AD

The Managing Director of TCN, Mr Usman Gur Mohammed disclosed this at the recent 24th monthly power sector meeting hosted by TCN in Abuja shortly after commissioning a 100MVA transformer at Katampe substation in Abuja.

 

The terminated projects he said are the Walalanbe and Danbatta transmission substation projects in Kano state and the GIT and Federal LLiod contracts under the Nigeria Electricity and Gas Improvement Programme (NEGIP).

 

Mr Mohammed said: "TCN engineers would complete all projects abandoned as well as those contractors that portrayed lack of capacity.  We have terminated the Walalanbe and Danbatta 132/33KV substation projects in Kano state and handed over the implementation to Kaduna transmission Region.

 

“The GIT and federal LLiod contracts under NEGIP and financed by World Bank have been handed over to Port Harcourt and Abuja Transmission Regions respectively,” he explained.

 

The Head of Projects, MBH Power, Rakesh Mahapatra at the event, said it is installing seven transformers under NEGIP and that four have been commissioned.

 

He said, “We have a 100MVA transformer right here in Katampe which has successfully increased the capacity of this substation. 

 

“Also, we have installed another 100MVA transformer in Apo. Furthermore, it might interest you to know that under this same project we are installing seven more transformers, out of which four have been commissioned,” Mahapatra said.

 

Mr Mohammed commended the MBH Power for meeting the specified timeline. “Messrs MBH Power did a marvellous job; they adhered to TCN new concept of speedy project delivery. They complied with our delivery schedule just as they did for Keffi and Apo substations,” the TCN boss noted.