TCN restores normal bulk power supply after Apo fire

TCN said it has restored normal power transmission through its Apo Transmission substation after a fire outbreak at about 1:33 pm involving one of its…

TCN said it has restored normal power transmission through its Apo Transmission substation after a fire outbreak at about 1:33 pm involving one of its 45MVA 132/33kV power transformers feeding AEDC’s 33kV feeders.

The fire was put off by the combined efforts of the Federal, FCT and NNPC fire service. It is however still early for TCN to determine if the burnt transformer can be salvaged.

In the statement signed by the General Manager (Public Affairs), TCN said the fire resulted from a direct fault from one of Abuja Disco’s 33kV feeders which had a history of incessant trippings, the 33kV lacked protection.

Meanwhile, TCN said it is equally investigating possibility of transformer protection failure on its 45MVA power transformer. The 33kV feeder H13 circuit breaker and current transformer exploded while the 33kV outgoing transformer snapped causing the fire.

TCN however noted that the Apo Transmission Substation has other transformers and so, power supply to all the areas that take supply from the substation through AEDC will not be affected by the incident.

This is because the maximum load taken by AEDC from the burnt 45MVA transformer was 26MW. Meanwhile maximum load AEDC takes from the old 100MVA in the substation is 56.5MW while maximum load from the second 100MVA power transformer installed last year is 30.8MW.

Both however can take at full capacity, a total of 160MW against the 86.5MW, it noted.

Presently, TCN it is transmitting normal supply through the 2x100MVA 330/132kV and the second 45MVA 132/33kv power transformers in the substation.

The company has equally loaded the 26MW from the burnt transformer into the 100MVA MBH transformer at the substation and is adequately supplying AEDC without load reduction.

TCN said it is also working with the Abuja Electricity Distribution company to ensure that it now takes the load formally taken from the burnt transformer through the MBH 100MVA transformer.

LEARN AFFILIATE MARKETING: Learn How to Make Money with Expertnaire Affiliate Marketing Using the Simple 3-Step Method Explained to earn $500-$1000 Per Month.
Click here to learn more.

AMAZON KDP PUBLISHING: Make $1000-$5000+ Monthly Selling Books On Amazon Even If You Are Not A Writer! Using Your Mobile Phone or Laptop.
Click here to learn more.

GHOSTWRITING SERVICES: Learn How to Make Money As a Ghostwriter $1000 or more monthly: Insider Tips to Get Started. Click here to learn more.
Click here to learn more.

SECRET OF EARNING IN CRYPTO: Discover the Secrets of Earning $100 - $2000 Every Week With Crypto & DeFi Jobs.
Click here to learn more.