African Capital Alliance (ACA) and Elalan Group have indicated that the first set of apartments from their project, Blue Water Lagos (BWL), will be ready for use by December 2019.
BWL, which is the second largest multi-family residential development, will offer a unique lifestyle destination for Lagos residents, with an exciting blend of contemporary luxury apartments, state-of-the-art retail mall and an exclusive park.
The Managing Director of Elalan, Andrea Geday, in a statement, said Elalan commenced construction on this unique mixed-use development in July, 2017, with a commitment to deliver a product that catered to the taste, needs and aspirations of its residents while maintaining the speed and exceptional quality construction.
Obi Nwogugu of ACA was quoted to have said, “Blue Water residences offer ideal options for different homeowners looking for quality investment with unrivalled view of the Atlantic Coast, as well as easy and convenient access to shopping, dining, leisure and entertainment experiences, all within walking distance of their home at an affordable easy payment plan of 20 per cent initial down payment with the balance spread over the completion period.”
With Elalan Construction serving as the main contractor working with other notable building industry professionals, the developers are confident the project will be delivered on schedule and built to a standard that exceeds all expectations.
The project is divided into 3 Phases. Phase 1 consists of the first residential tower, Sapphire Residences and the recreational amenities including the resident’s park, basketball and tennis courts, adult and kid’s swimming pool and children’s playground.
The developers have confirmed they are on track to deliver Phase 1 of the project in time for Christmas 2019. The foundation is 80% complete with the basement car park at about 90%. The floor slabs are completed up to the 15thfloor with the 16thfloor at 20%and the lift shafts completed up to the 15thfloor and 35% at the 16th floor. The construction team is split into two groups with one handling the frame work and the other handling the finishing. There is an innovative batching plant for onsite concrete production to accelerate the construction process and eliminate time over run.
Commencement of the development’s numerous recreational amenities and procurement of the fixtures, fittings and finishing materials are scheduled to start before the end of the year in preparation for the final fix construction set to take place in 2019.
The Managing Director, Elalan Group, Andrea Geday stated:
“Our brand-new state of the art Sales Suite and Show apartment located on site at Plot 1, Block 5, Goshen Road, off RemiOlowude Street, Lekki Phase 1, Lagos is ready to receive clients and introduce them to this spectacular new project”.